Foothill Gold Line - February 2017 Project Status Memo
February 2017 Project Status Memo

In January, the Foothill Gold Line Construction Authority Board of Directors approved an updated project schedule for the 12.3-mile, six-station Foothill Gold Line light rail extension from Glendora to Montclair. The updated schedule is based on detailed constructability reviews conducted as part of the advanced conceptual engineering phase and a more extensive understanding that the next segment is really two major construction projects in one first the freight and Metrolink relocation/reconstruction, and then the light rail system construction.



( View PDF )